Please follow the guidelines below for installation of systems that generate up to 2MW. The interconnection applications for Pennsylvania are classified by level of complexity.

  • Level 1 — Certified inverter based installations with aggregate rating less than 10 kW
  • Level 2 — Certified inverter based installations with aggregate rating 10kW to 2,000 kW
  • Level 3 — Non-certified equipment 2,000 kW or less that will export power to PCL&P
  • Level 4 — Non-certified equipment 2,000 kW or less that will not export power to PCL&P
Interconnection Procedure for Level 1

Prior to Installation

  1. Applicant should send:
    • a letter of authorization by customer (if the applicant is an agent for the customer)
    • Part 1 of the Level 1 Interconnection Application/Agreement
    • three-line electrical schematic
    • site plan
    • copy of the manufacturer's data sheet and certification for the equipment
    • application fee for level 1 review ($100)
  2. PCL&P will review the application and design.
  3. PCL&P will either give approval to install the system or explain why approval was not granted.

Upon completion of installation

  1. Applicant should send in Part 2 of the Level 1 Interconnection Application/Agreement and proof of electrical inspection.
  2. PCL&P will witness the verification test.
  3. If the verification test is passed, PCL&P will return the executed application/agreement to applicant. (The system should not be put in service, except for initial testing, until after the verification test.)
  4. If the installation is eligible for net metering, PCL&P will change the revenue meter.
Interconnection Procedure for Level 2, 3 and 4

Prior to Installation

  1. Applicant should send:
    • a letter of authorization by customer (if the applicant is an agent for the customer)
    • Level 2, 3 or 4 Interconnection Application and Agreement
    • Attachment A – Description of Facility
    • three-line electrical schematic
    • copy of the manufacturer's data sheet and certification for the equipment
    • site plan
    • application fee
      • For level 2 application, the fee is $250 plus $1.00 per kW of the nameplate capacity rating
      • For level 3 application, the fee is $350 plus $2.00 per kW of the nameplate capacity rating
      • For level 4 application, the fee is $350 plus $2.00 per kW of the nameplate capacity rating
  2. PCL&P will review the application and design. We may require additional information depending on the complexity of the design.
  3. If additional feasibility studies and modification to the utility distribution system are required, PCL&P will notify the applicant and provide estimated costs for such study and or/modification.
  4. PCL&P will either approve the installation, or explain why approval was not granted.

Upon completion of installation

  1. Applicant should send in Attachment B of the Level 2, 3 or 4 Interconnection Application and proof of electrical inspection.
  2. PCL&P will witness the verification test at a mutually agreeable time.
  3. If the verification test is passed, PCL&P will return the executed net metering agreement to applicant. (The system should not be put in service, except for initial testing, until the system has passed the verification test.)
  4. If the installation is eligible for net metering, PCL&P will change the revenue meter.
Installations Greater Than 2MW

Please follow the applicable guidelines below for installation of systems that generate more than 2MW: